File #: 24-1431    Name:
Type: Recommendation Status: Consent Item Ready
File created: 11/1/2024 In control: City Council
On agenda: 12/9/2024 Final action:
Title: Approval of a contract modification with Poznecki-Camarillo Engineering for the completion of the plans, specifications, cost estimates, and construction administration of the South Kowald Lane Project.

PRESENTER: Presenter

Scott McClelland, Assistant Transportation and Capital Improvements Director

 

Body

SUBJECT: Title

Approval of a contract modification with Poznecki-Camarillo Engineering for the completion of the plans, specifications, cost estimates, and construction administration of the South Kowald Lane Project.

 

Header

DEPARTMENT: Transportation and Capital Improvements

 

 

 

Body                     

COUNCIL DISTRICTS IMPACTED: 5

 

BACKGROUND INFORMATION:

On May 9, 2022, City Council approved capital improvement projects for preliminary design or design updates in preparation for a proposed 2023 Bond Election that included preliminary design of South Kowald Lane by Poznecki-Camarillo Engineers.

 

The proposed project will expand the existing roadway to include a center turn lane between IH-35 and FM 1101. Turn lanes and traffic signal upgrades will be made at the intersections with IH-35, Sophie Lane, and FM 1101. Pedestrian improvements will be made by installing 6’ sidewalks on both sides of Kowald Lane. Improvements will also be made to the drainage infrastructure.

 

City Staff requested Poznecki-Camarillo provide an updated scope and fee for completion of the plans, specifications, cost estimates, and construction administration services. Poznecki- Camarillo submitted a proposal for an hourly not to exceed amount of $1,273,120.

 

 

 

 

ISSUE:

Continue an ongoing program of infrastructure, construction, and maintenance.

 

STRATEGIC PLAN REFERENCE:

☐Economic Mobility ☒Enhanced Connectivity ☐Community Identity

☐Organizational Excellence ☐Community Well-Being ☐N/A

 

Identify and establish planning, capital, and operating funding to

support and maintain a well-connected transportation network serving

pedestrians, bicyclists, transit users, children, older individuals, individuals

with disabilities, motorists, and freight vehicles.

 

FISCAL IMPACT:

Funding for this project was included in the 2023 Bond Proposition A, therefore sufficient funds are available.

 

 

 

Recommendation

RECOMMENDATION:

Approval of a contract modification with Poznecki-Camarillo Engineering for the completion of the plans, specifications, cost estimates, and construction administration of the South Kowald Lane Project.