Legislation Details

File #: 26-357    Name:
Type: Report Status: Passed
File created: 3/17/2026 In control: City Council
On agenda: 4/13/2026 Final action: 4/13/2026
Title: Approval of an expenditure of up to $1,300,000 for the acquisition of the necessary right-of-way and easements as part of the Common Street Project and authorization for the City Manager to execute all necessary conveyance documents.

PRESENTER: Presenter

Matthew Eckmann, Assistant Director of Public Works

 

Body

SUBJECT: Title

Approval of an expenditure of up to $1,300,000 for the acquisition of the necessary right-of-way and easements as part of the Common Street Project and authorization for the City Manager to execute all necessary conveyance documents. 

 

Header

DEPARTMENT: Public Works and Transportation and Construction Services

 

 

Body                     

COUNCIL DISTRICTS IMPACTED: Districts 4

 

 

BACKGROUND INFORMATION:

 

The Common Street Reconstruction Project from Loop 337 to FM 306 is one of the approved projects in Proposition A of the City of New Braunfels 2023 Bond Program.  The project will improve the current roadway to four lanes, improve drainage infrastructure, provide intersection enhancements and provide for sidewalks.

 

 

ISSUE:

 

In order to accomplish this project, it is necessary to acquire right-of-way, drainage easements, utility easements and temporary construction easements from approximately 62 parcels.  The City is contracted with Cobb Fendley to provide right-of-way acquisition services for this project.  Appraisals have been obtained and initial offers have been sent to property owners.

 

The expenditure shall be utilized for the purchase of right-of-way, public utility easements, drainage easements and temporary construction easements along with any damages for improvements (fencing, landscaping, etc) that will be affected by the acquisition.      

 

STRATEGIC PLAN REFERENCE:

Economic Mobility Enhanced Connectivity Community Identity

Organizational Excellence Community Well-Being N/A

 

FISCAL IMPACT:

Funds for the acquisition of right-of-way and easements are incorporated in the project budget utilizing 2023 bond funding.  

 

 

 

Recommendation

RECOMMENDATION:

Staff recommends approval of the expenditure and authorization for the City Manager to execute all necessary conveyance documents.