Title: Public hearing, discussion, and possible action approving a project expenditure, of up to $2,300,000, to the Headwaters at the Comal for the completion of construction, pursuant to Section 505.152 of the Texas Local Government Code.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PRESENTER: Presenter

Mandi Scott, Economic and Community Development Manager

Body

SUBJECT: Title

Public hearing, discussion, and possible action approving a project expenditure, of up to $2,300,000, to the Headwaters at the Comal for the completion of construction, pursuant to Section 505.152 of the Texas Local Government Code.

Header

DEPARTMENT: Economic and Community Development

Body                     

COUNCIL DISTRICTS IMPACTED: 4

 

BACKGROUND INFORMATION:

The New Braunfels Economic Development Corporation (“NBEDC”) approved an initial grant of $1.2M for the initiation of the Headwaters at the Comal project in March 2022. Since then, significant improvements have been completed at the site to include: main building repurposing, adding a front drive through, installation of recycled concrete pavers, hardscape features, rainwater cisterns and archeological discoveries. Additional work planned will complete the formal front entrance and picnic commons, air-conditioned spaces, visitor’s center, multiple meeting spaces and public restroom facilities; and an adjacent parking lot to support access to the Headwaters.

 

The NBEDC met on February 20, 2025 to consider a request from the Headwaters at the Comal for up to $2,300,000 to complete construction of the project. If this second grant is approved, the item will move for City Council approval on May 12, 2025.

 

ISSUE:

Additional funds are being requested by the Headwaters at the Comal to complete construction of the project at 333 E. Klingemann Street.

 

STRATEGIC PLAN REFERENCE:

Economic Mobility Enhanced Connectivity Community Identity

Organizational Excellence Community Well-Being N/A

 

FISCAL IMPACT:

The not to exceed amount for this second grant is $2,300,000; the NBEDC has sufficient funds to approve this expenditure.

Recommendation

RECOMMENDATION:

Staff recommends approval of the $2,300,000 for the completion of Phase 2 construction of the Headwaters at the Comal project.