Skip to main content
New Braunfels Logo
File #: 25-454    Name:
Type: Resolution Status: Passed
File created: 4/4/2025 In control: City Council
On agenda: 4/14/2025 Final action: 4/14/2025
Title: Approval of an increase in the contingency amount of an existing contract with Lone Star Site Work, LLC for construction of the Common Street Pedestrian Improvements project in the amount of $150,000.

PRESENTER: Presenter

Scott McClelland, Assistant Transportation and Capital Improvements Director

 

Body

SUBJECT: Title

Approval of an increase in the contingency amount of an existing contract with Lone Star Site Work, LLC for construction of the Common Street Pedestrian Improvements project in the amount of $150,000.

 

Header

DEPARTMENT: Transportation and Capital Improvements

 

Body                     

COUNCIL DISTRICTS IMPACTED: 4, 5

 

 

BACKGROUND INFORMATION:

On June 24, 2024, the City Council approved construction funding for the Common Street Pedestrian Improvement project from the 2023 Bond Fund.  This approval included the federal participation portion of the agreement with the Alamo Area Metropolitan Planning Organization, up to 80%, or $1,478,910, for any participating construction items.  All non-participating and construction overage items are the responsibility of the City of New Braunfels, which was funded by the New Braunfels Economic Development Corporation (NBEDC) in an amount not to exceed $700,000.

 

City Council approved a 10% contingency of $158,301, with the original contract. However, as construction has progressed, several utility conflicts were identified, and design revisions and construction costs to address these conflicts are not part of the federal participation reimbursement items.  Additional conflicts are anticipated before the completion of the project, and an increase in contingency is necessary. Staff requests an increase to the project contingency of $150,000, taking contingency from $158,301 to $308,301, utilizing a portion of the remaining available funds allocated by the NBEDC.

 

ISSUE:

Ensure sufficient approval for funds needed to complete construction of the Common Street Pedestrian Project.

 

 

STRATEGIC PLAN REFERENCE:

Economic Mobility Enhanced Connectivity Community Identity

Organizational Excellence Community Well-Being N/A

• Increase in walk and bike Score.

• Increased bikeway, trails, and sidewalk miles.

 

 

 

 

 

 

FISCAL IMPACT:

The NBEDC has approved funding up to $700,000 for the construction phase of this project. The total spend, including the proposed increase to the contingency amount, remains within that $700,000 funding amount, therefore, sufficient funds are available.

 

NBEDC Fund                     Contribution                                                                                                                         $700,000.00

 

City 20% Construction Participation                                                                                                    ($316,603.94)

 

                                         10% Contingency                                              ($158,301.00)

               Proposed Additional Contingency                                   ($150,000.00) 

Total contingency                                                                                                                            ($308,301.00)

 

Adjusted Total Spend                                                                                                                           ($624,904.94)

 

Remaining Funds                                                                                                                                               $  75,095.06

 

 

Recommendation

RECOMMENDATION:

Recommend approval of an increase to the contingency amount of an existing contract with Lone Star Site Work, LLC for construction services for Common Street Pedestrian Improvements in the amount of $150,000.