Title: Approval of a contract with T.F. Harper & Associates for construction services on Airport Terminal Repairs and authorization for the City Manager to approve any change orders up to a ten percent contingency as well as all other necessary project expenditures.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Presenter/Contact

Presenter

Jennifer Cain, Capital Programs Manager

Contact Info

(830) 221-4646 - JCain@nbtexas.org

 

Subject Header

SUBJECT:

Title

Approval of a contract with T.F. Harper & Associates for construction services on Airport Terminal Repairs and authorization for the City Manager to approve any change orders up to a ten percent contingency as well as all other necessary project expenditures.

 

Body

BACKGROUND / RATIONALE:

In August 2017 the New Braunfels Regional Airport sustained damage as a result from Hurricane Harvey. The City had a facility assessment performed on the Airport Terminal and Control Tower Buildings. The City has filed property claims with FEMA and its insurance carrier, TML. The claims process is lengthy due to the many Texas claims resulting from Hurricane Harvey. If the City receives Claim funds from the FEMA and/or its property insurance, they will supplant the funds expended.

 

On November 27, 2017, City Council approved Debra Dockery & Associates to assess the damage and develop construction documents for renovations.  The renovations include new wood framing, drywall, insulation, flooring and caulking along windows and roof penetrations. It also includes demolishing existing sidewalks around the building and re-grading the areas to add new sidewalks that will improve the drainage around the building.

 

On March 14, 2018 the project was issued for bid. The City received four bids on April 12, 2018. with T. F. Harper & Associates as the low bidder for the project with a cost of $148,345. The total cost of construction including a ten percent contingency is $163,180.

 

 

ADDRESSES A NEED/ISSUE IN A CITY PLAN OR COUNCIL PRIORITY:

X

Yes

City Plan/Council Priority:

Strategic Priorities: Continue an ongoing program of infrastructure construction and maintenance.

 

 

FISCAL IMPACT:

Funds were appropriated for an airport fuel truck which will be transferred for construction repairs.

 

If the City receives Claim funds from the FEMA and/or its property insurance, they will supplant the funds expended.

 

Recommendation

COMMITTEE RECOMMENDATION:

N/A

 

STAFF RECOMMENDATION:

Staff recommends approval of a contract with T.F. Harper & Associates for construction services on Airport Terminal Repairs and authorization for the City Manager to approve any change orders up to a ten percent contingency as well as all other necessary project expenditures.