Approval for a sewer connection fee on the Zipp Family Sports Park to Guadalupe-Blanco River Authority.
Header
DEPARTMENT: Transportation and Capital Improvements
Body
COUNCIL DISTRICTS IMPACTED: 2
BACKGROUND INFORMATION:
As part of an agreement with Guadalupe-Blanco River Authority (GBRA) approved by City Council on March 9, 2020, the City paid for an off-site sewer easement, design work, and a portion of new sewer main lines that would serve the Zipp Family Sports Park. In the agreement, connection fees were called out as a future expense the City would be responsible to pay once the Zipp Family Sports Park was constructed and tied into the GBRA owned sewer lines.
SpawGlass General Contractors has constructed and completed all on-site sewer lines and made the tie-in to the GBRA sewer main line. The connection fee invoice has been submitted to the City from GBRA for $55,200.
ISSUE:
Continue an ongoing program of infrastructure, construction and maintenance
STRATEGIC PLAN REFERENCE:
☐Economic Mobility ☐Enhanced Connectivity ☐Community Identity
☐Organizational Excellence ☒Community Well-Being ☐N/A
FISCAL IMPACT:
Sufficient funds are available in the project budget to support this expense.
Recommendation
RECOMMENDATION:
Approval of an expense for the sewer connection fee on the Zipp Family Sports Park to Guadalupe-Blanco River Authority.