Title: Approval for the City Manager to enter into a professional services agreement with Cobb Fendley to provide engineering design, bid phase and construction phase services for San Antonio Street, from Academy Street to Walnut Avenue, as part of the 2013 Bond Program.
Attachments: 1. Revised San Antonio Street Scope & Fee
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Presenter/Contact

Presenter

Jennifer Cain, Capital Programs Manager

Contact Info

(830) 221-4646 - jcain@nbtexas.org

 

Subject Header

SUBJECT:

Title

Approval for the City Manager to enter into a professional services agreement with Cobb Fendley to provide engineering design, bid phase and construction phase services for San Antonio Street, from Academy Street to Walnut Avenue, as part of the 2013 Bond Program.

 

Body

BACKGROUND / RATIONALE:

The City-wide street program was approved by the citizens in the 2013 Bond Election. Projects in this program could include: mill & overlay, curb repair/replacement, sidewalk repairs, and ADA improvements. 

 

On March 26, 2018 Council approved to move forward with San Antonio Street rehabilitation from Academy Street to Walnut Avenue.  On June 12, 2018 the City released an Request for Qualifications (RFQ) for the Alamo Area Metropolitan Planning Organization (AAMPO) funded City-wide Pedestrian Improvement project which includes the removal and/or replacement of City sidewalks in various locations.  One location chosen as part of the Pedestrian Improvements project parallels the same “footprint” as the San Antonio Street project, Academy to Walnut Ave.  It is recommended by staff to utilize Cobb Fendley for the roadways improvements as well to improve coordination between the two projects and to benefit from this turn-key opportunity.  Cobb Fendley has the experience and resources available to take-on both projects simultaneously.   

    

As of October 16, 2018, NBU has initiated their construction contract for the replacement of the existing sewer and water utility in this location and is contracted to run through June 2019 which will allow time for the proposed design of the roadway improvements.

 

 

ADDRESSES A NEED/ISSUE IN A CITY PLAN OR COUNCIL PRIORITY:

X

Yes

City Plan/Council Priority

Strategic Priorities: 3 - Continue an ongoing program of infrastructure construction and maintenance

 

 

FISCAL IMPACT:

The total costs for professional services to complete the engineering design and all subsidiary tasks, which will include plans, specifications and cost estimates will be $79,806.50. There are sufficient funds remaining in the 2013 Bond Program for this work.

 