File #: 20-891    Name:
Type: Report Status: Consent Item Ready
File created: 11/30/2020 In control: City Council
On agenda: 2/22/2021 Final action:
Title: Approval of the Final Addendum to the Development Agreement for Roadway Impact Fee Offsets between the City of New Braunfels and Milestone Crest Investments, LTD authorizing payment of excess costs of constructing Pahmeyer Road within the Silos Subdivision and authorizing the city manager to execute the agreement.
Attachments: 1. Development Agreement Silos U3 Addendum, 2. Development Agreement Silos U3 Addendum Exhibits
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Presenter/Contact

Presenter

Garry Ford, Assistant Public Works Director/City Engineer

Contact Info

(830) 221-4020 - gford@nbtexas.org

 

Subject Header

SUBJECT:

Title

Approval of the Final Addendum to the Development Agreement for Roadway Impact Fee Offsets between the City of New Braunfels and Milestone Crest Investments, LTD authorizing payment of excess costs of constructing Pahmeyer Road within the Silos Subdivision and authorizing the city manager to execute the agreement.

 

Body

BACKGROUND / RATIONALE:

On October 11, 2017, the City of New Braunfels and Milestone Crest Investments, LTD entered into a Development Agreement and Settlement Agreement to settle all disputes concerning development and approval of the Silos Subdivision pertaining to the construction and dedication of right-of-way for a minor collector street within the subdivision and offsets against roadway impact fees due.

 

The City of New Braunfels and Milestone Crest Investments, LTD have negotiated a Final Addendum to the Development Agreement for the payment of the excess cost of constructing the minor collector street within the subdivision over the cost of constructing a local street for the Silos Subdivision Units 1 and 2 in the amount of $174,454.00 and Unit 3 in the amount of $59,331.29. The minor collector street for all units has been constructed and accepted by the City in accordance with the City of New Braunfels Code of Ordinances and sufficient roadway impact fees have been collected to pay the excess costs which are $233,785.29.

 

ADDRESSES A NEED/ISSUE IN A CITY PLAN OR COUNCIL PRIORITY:

N/A

 

FISCAL IMPACT:

Milestone Crest Investments, LTD will receive payment of $233,785.29 from Roadway Impact Fees Fund Service Area 5. The current balance of Roadway Impact Fees Fund Service Area 5 is $1,788,803.71.

 

Recommendation

COMMITTEE RECOMMENDATION:

N/A

 

STAFF RECOMMENDATION:

Staff recommends approval of the Final Addendum to the Development Agreement for Roadway Impact Fee Offsets between the City of New Braunfels and Milestone Crest Investments, LTD.